ERP data migration: from scope to go-live, step by step

Version 1.0 — Last updated:

How do you migrate data into a new ERP? Decide what moves: master data, open items, opening balances and, only if needed, history. Give each data type an owner, clean it in the old system and map it to the new structure. Run trial loads, reconcile the totals, then go live on a fixed cutover date, with a short parallel run if the risk justifies it.

Data migration means moving information from your existing systems into the new ERP so that it arrives complete, correct and checked. This guide from Turkey-based Gramoni sets out steps that apply whichever product you implement. It is written for companies operating in Turkey, including international groups replacing a local subsidiary's system. For the overall project, see ERP implementation phases; for choosing a product and partner, see the ERP selection guide.

Why data migration is its own workstream

Every report and every automatic posting in the new ERP depends on the data loaded into it. Xu and colleagues' case study of two large Australian organisations concludes that data quality is a critical issue in ERP implementation and that its importance needs to be widely understood across the project (Industrial Management & Data Systems, 2002).

The cause is usually organisational, not technical. In Haug and Stentoft Arlbjørn's survey of 90 Danish companies, the barrier with the greatest effect on master-data quality was a lack of delegated responsibility for maintaining master data (Journal of Enterprise Information Management, 2011). In a separate paper the same lead author argues that the goal is not perfect data but an optimal quality level, balanced against the cost of getting there (Journal of Industrial Engineering and Management, 2011).

ERP research lists data work among the success factors. A 2025 study based on a panel of 31 information-systems experts and case studies of five companies includes "data analysis and conversion" among its 25 critical success factors (Ferrer-Gilabert et al., 2025).

So data migration is not a load run in the last week before go-live. It is a workstream with its own plan, owners and acceptance criteria.

1. Scope: what moves?

The first decision is what moves and what stays behind. Treat each group of data separately.

Data groupExamplesUsual approach
Master dataProduct and stock items, customer and supplier cards, chart of accounts, bills of materials, warehouse and shelf locations, employeesMigrated after cleansing and restructuring for the new system.
Open itemsOpen sales and purchase orders, unpaid invoices, open work orders, outstanding cheques and promissory notesMigrated document by document as at the cutover date.
Opening balancesStock quantities and values, customer and supplier balances, bank and cash balances, trial balanceMigrated as at the cutover date and proven by reconciliation.
Transaction historyPrior years' invoices, stock movements and journal entriesA separate decision: migrate as summaries, or keep the old system as a read-only archive.

Get the scope decision in writing. "Let's move everything" also means moving every error in the old system.

2. Give every data type an owner

Product data usually belongs to production or purchasing, customer and supplier data to sales and finance, and the chart of accounts to accounting. The data owner is responsible for:

  • Deciding the rules for cleansing the data.
  • Filling in, or having someone fill in, the template with their unit's data.
  • Checking and signing off the data after each trial load.

The implementation partner supplies the templates, field rules and checks. The business decides which record is right.

3. Cleansing: fix data before you move it

Clean data in the old system, before migration. Common problems:

  • Several customer or supplier cards for the same company.
  • Missing or wrong tax ID numbers (VKN), IBANs or addresses.
  • Stock items with no movement for years.
  • The same product opened under different units or names.
  • Out-of-date bills of materials and routings.

Write a rule for each problem: which record stays, which merges, which closes. As Haug and colleagues point out, perfection is not the target. Fix first the errors that would block go-live or corrupt reports.

4. Mapping: from the old structure to the new

Write down in a mapping table where each field in the old system goes in the new ERP.

  • Code structures: what will item codes, customer codes and account codes look like?
  • Value lists: units, currencies, payment terms, tax rates, warehouse codes.
  • Mandatory fields: who supplies information the new ERP requires but the old system never held?
  • Transformation rules: merged or split fields, changed units.

The mapping table must match the processes signed off in design. If a process changes, the mapping changes with it.

5. Trial loads

Load the data into a test environment at least once; most projects do it several times.

  • List load errors and business-rule errors separately after each trial.
  • Fix errors at the source, in the old system or the template, not by hand in the new system.
  • Have key users run their test scenarios on the loaded data. Testing with real data catches errors that sample data cannot.

One of the companies studied by Ferrer-Gilabert and colleagues reports that continuous testing throughout configuration let the new system settle well before the final switch (2025).

6. Reconciliation

Reconciliation proves, with numbers, that the migrated data is complete and correct. Compare these values for the same date in the old and new systems:

  • Record counts per data type.
  • Customer and supplier balance totals and ageing.
  • Stock quantity and value per warehouse.
  • Trial balance.
  • Open order and open invoice totals.

Explain every difference in writing. The data owner signs off the reconciliation report; data without sign-off does not go live.

7. The cutover plan

Plan go-live hour by hour.

  • Cutover date: the date the opening balances are taken. Usually a month-end or period-end.
  • Freeze: which master-data changes stop before cutover, and which transactions close in the old system.
  • Sequence: master data first, then opening balances, then open items.
  • Check and sign-off: reconciliation of the final load and approval by the data owners.
  • Go/no-go: the conditions under which go-live is postponed, written down in advance.

Large IT projects often overrun: in Flyvbjerg and Budzier's study of 1,471 IT projects the average cost overrun was 27% (Harvard Business Review, 2011). Giving data migration its own, realistic place in the schedule makes part of that risk visible.

8. Parallel run

In a parallel run, the same transactions are also entered in the old system for a period after go-live. It builds confidence but doubles the workload.

  • Consider it only for critical processes.
  • Announce the end date up front; an open-ended parallel run keeps users tied to the old system.
  • Compare results regularly during the period and close the differences.

Data migration checklist

  • The data groups that move, and those that do not, are written down.
  • The decision on history and the archive method are clear.
  • Every data type has an owner.
  • Cleansing rules are written and applied in the old system.
  • The mapping table matches the signed-off processes.
  • At least one trial load was run and tested by key users.
  • Reconciliation reports are signed off by the data owners.
  • The cutover date, freeze rules and load sequence are written down.
  • If there is a parallel run, its end date is announced.

How Gramoni handles this in Workcube projects

Gramoni is a Workcube partner and implements Workcube, a Turkish ERP platform, using Workcube's eight-phase implementation methodology, with a written output at every phase. In that methodology, master-data migration is part of the Configuration phase. The same team quotes the project, writes the code and takes it live, and the project can be run in English.

See Workcube ERP consulting for details.

Frequently asked questions

Which data should move to the new ERP?

At a minimum, master data (products, customers and suppliers, chart of accounts, bills of materials, warehouses), open items (open orders, unpaid invoices, open work orders) and opening balances (stock, customer and supplier balances, bank, general ledger). Whether history moves is a separate decision; often the old system is kept as a read-only archive.

Do we need to migrate several years of transaction history?

Not always. Moving history multiplies the mapping and reconciliation work. Write down what reporting and statutory retention actually require. If people only need to look things up, keeping the old system or an export accessible is often enough.

Who should clean the data?

The department that owns it. The implementation partner supplies the templates, field rules and checks, but the business decides which customer records are duplicates and which stock items close. In a survey of 90 Danish companies, the biggest barrier to master-data quality was that nobody had been given responsibility for maintaining it.

How many trial loads are enough?

There is no fixed number. The rule is that you do not go live until the last trial load runs clean and reconciles. Errors found in each trial are fixed at the source, not patched in the template.

How is reconciliation done?

Compare totals for the same date in the old and new systems, such as record counts, customer and supplier balances, stock quantity and value, and the trial balance. Every difference is explained in writing and signed off by the data owner.

Is a parallel run always necessary?

No. A parallel run builds confidence but doubles the workload. Use it for critical processes, for a short period announced in advance, with an end date fixed from the start.

Sources

  1. Xu, Nord, Brown & Nord — Data quality issues in implementing an ERP (2002) — Industrial Management & Data Systems
  2. Haug & Stentoft Arlbjørn — Barriers to master data quality (2011) — Journal of Enterprise Information Management
  3. Haug, Zachariassen & van Liempd — The costs of poor data quality (2011) — Journal of Industrial Engineering and Management
  4. Ferrer-Gilabert, Forés & Lapiedra — Stages and Critical Success Factors in ERP Implementation: Insights from Five Case Studies (2025) — Computer Science and Information Systems
  5. Flyvbjerg & Budzier — Why Your IT Project May Be Riskier Than You Think (Harvard Business Review, 2011) — arXiv