ERP implementation phases: from analysis to post-go-live support

Version 1.0 — Last updated:

What are the phases of an ERP implementation? Typically analysis and scope, process design, configuration and development, data migration, testing and user acceptance, training, go-live and post-go-live support. Names and counts vary by methodology. Each phase should end with a written deliverable, and your own team carries decisions, data and testing throughout.

An ERP implementation moves a company's processes onto a new system. This guide from Turkey-based Gramoni lists the phases you will go through whichever product you implement, what each phase needs from your own team and which deliverables you should receive. It is written for companies operating in Turkey, including international groups rolling out an ERP at a Turkish subsidiary. For choosing a product and partner, see the ERP selection guide; for moving the data, see ERP data migration.

Why the number of phases varies

Researchers do not agree on how many phases an ERP project has. A 2025 study compares the most-cited ERP life-cycle models, which propose between two and seven stages. One of the most widely used, Markus and Tanis's model, has four: chartering, project, shakedown, and onward and upward. The authors' own model has five: analysis, adoption, project, delivery and stabilisation, and continuity and improvement (Ferrer-Gilabert et al., 2025).

Implementation partners' methodologies break these down further. The eight phases below group the work a company sees during a project in a practical order.

The phases at a glance

PhaseWhat your team owesTypical deliverable
1. Analysis and scopeGoals, priorities and an executive sponsorWritten scope, budget and timeline
2. Process designProcess owners in the workshops, design sign-offProcess design documents, workflow diagrams, fit-gap list
3. Configuration and developmentQuick answers to open questions, feedback at interim demosConfigured system, custom development, reports, integrations
4. Data migrationData ownership, cleansing, filled templates, reconciliation sign-offMigration files, reconciliation reports
5. Testing and user acceptanceKey users running the scenariosTest scenarios, defect log, signed acceptance test
6. TrainingUsers released for trainingTraining plan, user documentation
7. Go-liveSticking to the cutover date, retiring the old waysCutover checklist, go-live decision
8. Post-go-live supportRequests through one channel, presence at the first closesSupport log, status reports, improvement list

1. Analysis and scope

This phase writes down why the project exists, what it covers and what success looks like.

  • Work done: needs analysis, the list of modules and processes in scope, budget and timeline.
  • From your team: an executive sponsor with decision authority, a project manager and one key user per department.
  • Deliverable: written scope and timeline. This is the text that should go into the contract.

PMI's 2017 Pulse of the Profession puts lack of defined objectives and milestones (37%) at the top of the reasons projects fail. This phase exists to close that gap.

2. Process design

How each process will run in the new system is designed in writing.

  • Work done: analysis of today's processes, design of the target processes, and a fit-gap analysis of standard features against requirements.
  • From your team: the people who run each process attend the workshops, and decisions are made on time.
  • Deliverable: a design document per process, workflow diagrams, a draft authorisation matrix, and sign-off.

Starting configuration before design is signed off means doing the work twice.

3. Configuration and development

The signed-off design is built into the system.

  • Work done: parameters, screen and process settings, reports, integrations, and custom development where standard screens do not cover a requirement.
  • From your team: quick answers to open questions and feedback at interim demos.
  • Deliverable: a configured test environment and a list of custom developments.

Ask whether custom development changes the product's standard code. If it does, every update means rework.

4. Data migration

In most projects data migration runs alongside configuration rather than starting just before go-live. Scope, cleansing, mapping, trial loads and reconciliation form their own workstream; see the ERP data migration guide.

  • From your team: an owner for each data type, cleansing, filled templates and reconciliation sign-off. In a survey of 90 Danish companies, the biggest barrier to master-data quality was that nobody had been given responsibility for maintaining it (Haug and Stentoft Arlbjørn, 2011).
  • Deliverable: migration files and signed-off reconciliation reports.

5. Testing and user acceptance

The system is tested end to end against the signed-off processes.

  • Work done: unit tests, end-to-end process tests (quote to order to delivery to invoice, for example), integration tests, and user acceptance testing.
  • From your team: key users run the scenarios with their own data and sign off the results.
  • Deliverable: test scenarios, a defect log and a signed acceptance test.

"Software development, testing and troubleshooting" is one of the 25 critical success factors in Ferrer-Gilabert and colleagues' study. One of the companies they studied reports that continuous testing throughout configuration let the new system settle well before the final switch (2025).

6. Training

Users learn the new process before go-live.

  • Work done: key-user training first, then end-user training, ideally on the company's own data.
  • From your team: users actually released for training. Key users training their own teams makes it stick.
  • Deliverable: training plan, attendance list, user documentation.

"User training and education" is also among the 25 factors in the same study (2025). A 2025 systematic literature review published in Turkey highlights user training together with scope management, risk analysis, resource planning, senior management support and change management (Yönetim Bilişim Sistemleri Dergisi).

7. Go-live

The system opens for real use.

  • Work done: final data load and reconciliation, closing the cutover checklist, the go-live decision.
  • From your team: keeping to the cutover date, closing transactions in the old system on schedule, dropping parallel spreadsheets.
  • Deliverable: a closed cutover checklist and a written go-live decision.

Go-live can be a single cutover or phased by module, company or site. If needed, the old system runs in parallel for a period announced in advance.

8. Post-go-live support

The first weeks are a period of intensive support. Ferrer-Gilabert and colleagues' model separates this "delivery and stabilisation" period from the "continuity and improvement" that follows.

  • Work done: user questions, fixes, support for the first month-end and period-end closes; then maintenance, updates and improvement.
  • From your team: requests sent through one channel, via the key users.
  • Deliverable: a support log, regular status reports and an improvement list.

Work that runs through every phase

Some work belongs to no single phase.

  • Sponsor: PMI's 2017 study names an actively engaged executive sponsor as the top driver of project success. In the same study, poor communication (19%) and lack of communication by senior management (18%) are the second and third reasons for failure.
  • Scope management: every scope change is recorded in writing, with its effect on budget and timeline discussed at the same time.
  • Change management: users should first hear about the new process in design, not in training.
  • Team continuity: one of the companies in Ferrer-Gilabert and colleagues' study cites a change of consultant during the project stage as one cause of its delay (2025).

When this work is neglected, overruns grow. In Flyvbjerg and Budzier's study of 1,471 IT projects, the average cost overrun was 27%, but one project in six had an average cost overrun of 200% and a schedule overrun of almost 70% (Harvard Business Review, 2011).

How Gramoni handles this in Workcube projects

Gramoni is a Workcube partner and implements Workcube, a Turkish ERP platform, using Workcube's eight-phase implementation methodology: Selection, Planning, Technology setup, Design, Configuration, Go-live and training, Support, and Sustainment. Each phase has a written output. The modules Gramoni implements include finance and accounting, CRM, HR, sales and distribution, and materials and production.

See Workcube ERP consulting for details.

Frequently asked questions

How many phases does an ERP project have?

There is no single right number. Models in the research literature range from two to seven stages, and implementation partners' methodologies are often more detailed still. What matters is that every phase has a written deliverable and a sign-off point.

What does the customer team owe the project?

Decisions, data and testing. The company decides how its processes will work, its departments prepare the master data, and its key users run the acceptance tests. If time for this is not set aside, the schedule will not hold.

What is a key user?

An employee from each department who knows the process well and can make decisions. Key users join the design workshops, run the tests, train their own teams and are the first point of support after go-live.

What is user acceptance testing?

The customer's own check, using business scenarios and ideally real data, that the new system does what the signed-off processes require. No go-live decision is made before the acceptance test is signed.

Should go-live be a single cutover or phased?

Both work. A single cutover is faster but concentrates the risk on one day; a phased go-live moves module by module, company by company or site by site. For a group, a Turkish subsidiary can be its own phase. The choice depends on dependencies between processes and on the team's capacity, and is written into the cutover plan.

Does the project end at go-live?

No. The first weeks are a period of intensive support, with user questions, small fixes and the first month-end close. After that the system moves into regular maintenance, updates and improvement.

Sources

  1. Ferrer-Gilabert, Forés & Lapiedra — Stages and Critical Success Factors in ERP Implementation: Insights from Five Case Studies (2025) — Computer Science and Information Systems
  2. PMI — Pulse of the Profession 2017 (infographic) — Project Management Institute
  3. Flyvbjerg & Budzier — Why Your IT Project May Be Riskier Than You Think (Harvard Business Review, 2011) — arXiv
  4. ERP Sistemlerinin Kurulumunda Proje Yönetimi: Sistematik Literatür Taraması (2025) — Yönetim Bilişim Sistemleri Dergisi
  5. Haug & Stentoft Arlbjørn — Barriers to master data quality (2011) — Journal of Enterprise Information Management