Quote costing in manufacturing: from material to margin, for make-to-order
Version 1.0 — Last updated:
In make-to-order manufacturing, a quote cost is built from material and scrap, labour and machine cost based on set-up and run times, outside processing and allocated production overhead; margin goes on top. To stay accurate, the quote must draw on current prices and times, and be compared line by line with actual cost when the order closes.
A make-to-order manufacturer has to price a product before making it. When a mould, a machine, a conveyor or a custom filter is quoted, there is no BOM or routing yet; both are estimated inside the quote. This guide from Turkey-based Gramoni explains which lines a quote cost is built from, how overhead is allocated, why spreadsheet quotes drift away from actual cost and how to compare quoted with actual. It is vendor-neutral, and it notes where Turkish accounting rules apply, for international companies manufacturing in Turkey.
What goes into a quote cost?
| Line | How it is calculated | Common mistake |
|---|---|---|
| Material | Quantity derived from dimensions and weight × current purchase price | Old prices; quantities guessed rather than derived |
| Scrap | Material quantity × expected scrap rate | Left out, or a different rate on every quote |
| Set-up time | Once per operation × hourly rate | Forgotten, so small orders look cheap |
| Run time | Unit time × quantity × machine and labour rates | Times copied from a similar job |
| Outside processing | Supplier quote + transport | Not updated after the quote date |
| Production overhead | Machine or labour hours × allocation rate | A rate calculated years ago |
| Administration and selling | Separate rate or amount | Mixed into production cost |
| Margin | On top of total cost | Cost and price kept in the same cell |
How cost is estimated
Niazi and colleagues' review of product cost estimation divides methods into two families: qualitative (intuitive and analogical) and quantitative (parametric and analytical) (Journal of Manufacturing Science and Engineering, 2006). The same review stresses how much cost estimation matters in the early phases of design.
At the quoting desk, the split looks like this:
- Intuitive: an experienced estimator says "this job is worth about so much". Fast, but it depends on one person, and nobody can see why the figure came out that way.
- Analogical: an old quote for a similar part is opened and adjusted. The most common method; the old quote's mistakes come along too.
- Parametric: a template is built for a part family, and material quantity and times are derived from parameters such as dimensions, weight and cavity count.
- Analytical: each operation is costed separately. The most detailed method, used as the design firms up.
For make-to-order work, the practical balance is usually a parametric template: parts in the same family are costed with the same logic, and only the parameters change.
Material and scrap
When material quantity is derived from the part's own dimensions, the quote becomes repeatable. For a sheet-metal part it comes from the flat-pattern size and thickness; for a casting or a moulded part, from weight and cavity count.
Keep scrap as its own line. Under TMS 2 Inventories, the Turkish accounting standard aligned with IFRS, abnormal amounts of wasted materials are not part of inventory cost; they are expensed in the period (paragraph 16). For quoting, that means: measure expected scrap and show it on the quote. Hiding scrap as a "safety margin" inside the markup means the real scrap rate is never learned.
Labour and machine time
Estimate two times for each operation:
- Set-up time is spent once per batch: mounting the mould or tool, adjustment, first-piece approval.
- Run time is spent per unit or per batch.
Cost is time multiplied by the hourly rate. Separate machine and labour rates give a realistic difference between machines with different levels of automation. Without set-up time, a one-off order and a hundred-piece order cost the same per unit, which is the most common way to lose money on small orders.
Allocating production overhead
Rent, depreciation, maintenance, energy, supervisors and the quality team cannot be charged directly to one order. They are allocated by a rate: the period's production overhead divided by the period's capacity, in machine hours or labour hours.
The divisor decides the rate:
- TMS 2 requires fixed production overhead to be allocated on the basis of normal capacity for inventory valuation. The amount per unit is not increased because of low production or idle plant; unallocated overhead is expensed in the period (paragraph 13).
- Kaplan and Anderson, in time-driven activity-based costing, ask for only two estimates: the cost per time unit of supplying capacity, and the time each job consumes. As a rough guide, they put practical capacity at 80–85% of theoretical capacity (HBS Working Knowledge, 2005).
Both point the same way: do not recalculate the rate every month from actual utilisation. When utilisation falls, the rate rises, quotes get more expensive, orders are lost and utilisation falls further. Fix the rate on normal or practical capacity and review it periodically.
Margin and price
Keep cost and price on separate lines. Cost answers "what does this job cost us?"; price answers "what do we charge this customer?". A customer contract price, a category discount or a negotiated figure changes the price; it should not change the cost calculation. If the two share a cell, nobody knows on the next quote which number was the real cost.
Why spreadsheet quotes drift from actual cost
Most job shops start quoting in a spreadsheet. The problem is not the spreadsheet itself; it is that over time the file loses its link to the real data in the ERP.
- Prices freeze. Material and subcontract prices are typed in once, with no link to current purchasing prices.
- Rates age. The hourly rate and overhead rate were calculated years ago and never updated.
- Copies breed copies. A new quote starts from an old one, and the old error is copied with it.
- Knowledge stays with one person. Only the person who built the file knows the logic behind the formulas.
- Formula errors are invisible. In the field audits Panko reviewed, the more recent audits, which used better methods, found errors in at least 86% of the spreadsheets examined (EuSpRIG, 2000).
- There is no feedback. Once the quote is accepted, actual cost never returns to the same file, so nobody learns which estimates held.
Comparing quoted and actual cost
You only learn how accurate a quote was by comparing it with actual cost.
- Same breakdown: the quote lines (material, scrap, set-up, run, outside processing, overhead) should be tracked under the same names in actual cost. A quote kept as a single total cannot be compared.
- Conversion on acceptance: an accepted quote should become a product card, a BOM and a routing, so production starts from the quote's assumptions and variances can be traced.
- Comparison at close: when the order closes, read quantity, time and price variances separately for each line.
- Feedback: feed recurring variances back into the part-family template, scrap rates and times. TMS 2 likewise expects standard costs to be reviewed regularly and revised where needed (paragraph 21).
Checklist
- Each part family has a written cost template.
- Material quantity is derived from dimensions and weight; scrap is a separate line.
- Every operation has separate set-up and run times.
- Material and subcontract prices come from a current price list.
- The overhead rate is based on normal or practical capacity, and its date is known.
- Cost and price (margin, discount, contract price) sit on separate lines.
- An accepted quote becomes a product card and a BOM.
- Quoted and actual cost are compared line by line on closed orders.
What Gramoni does here
Gramoni is a Workcube partner; Workcube is a Turkish ERP platform. WAMS Quotation & Cost Management (WAMS stands for Workcube Advanced Manufacturing System) is a Workcube ERP add-on for make-to-order manufacturers. A cost recipe derived from the part's own dimensions becomes a priced quote, and an accepted quote becomes a Workcube product card and multi-level BOM in one step.
- Reusable cost recipes by part family.
- Quantities derived from dimensions, weight, cavity count and scrap.
- Prices from Workcube price lists, category prices and contract exceptions.
- Estimated and actual cost side by side, with role-based visibility.
- An accepted quote becomes a product card, a multi-level BOM and a specification version in one step.
What it does not do: production planning, work orders, MRP, purchase requests, quality control and CAD/CAM. It is built for make-to-order and project manufacturers such as mould, machinery, conveyor and industrial bag filter makers, not for companies selling standard catalogue products.
Details and the pricing model are on the manufacturing solutions for Workcube page. Once an accepted quote has become a BOM, the guide to work orders and bills of materials explains how work orders, stock and cost connect.
Frequently asked questions
What should a manufacturing quote cost include?
Material and scrap, labour and machine cost per operation based on set-up and run times, outside processing, packaging and freight where relevant, and allocated production overhead. Administration and selling costs and the margin go on top as separate lines.
How is production overhead charged to a quote?
Usually as a rate per machine hour or labour hour, found by dividing the period's production overhead by capacity. Which capacity you divide by changes the answer. TMS 2, the Turkish inventory standard, uses normal capacity for inventory valuation.
How should scrap be handled in a quote?
Add expected scrap to material quantity as a rate and keep it visible on the quote. Under TMS 2, abnormal waste is expensed in the period rather than added to inventory cost. Measuring normal scrap properly works better than hiding a safety allowance in the margin.
What is wrong with quoting in spreadsheets?
Prices, hourly rates and formulas stay in one person's file, get copied from old quotes and are rarely updated. In the field audits Panko reviewed, the more recent audits found errors in at least 86% of the spreadsheets examined (2000). And the quote cannot be compared with actual cost automatically.
When should quoted and actual cost be compared?
When the order or work order closes, using the same cost lines as the quote. Read material quantity, time and price variances separately, and feed recurring variances back into the rates and times used for the next quote.
Do similar parts have to be costed from scratch every time?
No. Build a cost template per part family and derive quantities and times from parameters such as dimensions and weight. The literature calls this parametric cost estimation. Only the parameters change from quote to quote.
Sources
- KGK — TMS 2 Inventories (Turkish Accounting Standard) — Public Oversight, Accounting and Auditing Standards Authority (KGK)
- Kaplan & Anderson — Rethinking Activity-Based Costing (HBS Working Knowledge, 2005) — Harvard Business School
- Panko — Spreadsheet Errors: What We Know. What We Think We Can Do (EuSpRIG, 2000) — arXiv / European Spreadsheet Risks Interest Group
- Niazi, Dai, Balabani & Seneviratne — Product Cost Estimation: Technique Classification and Methodology Review (2006) — Journal of Manufacturing Science and Engineering (ASME)